Ans .
(4)21 days
(2) B`s 1 days work = (A + B)s 1 days work - A`s 1 day`s work=\( \frac{1}{12} \)-\( \frac{1}{28} \)= \( \frac{7-3}{84} \)=\( \frac{4}{84} \)=\( \frac{1}{21} \). Required time = 21 days.
Ans .
(4) (\( \frac{mn}{m+n} \)) days
4) A`s 1 days work =\( \frac{1}{m} \)and B`s 1 days work =\( \frac{1}{n} \) (A + B)s 1 days work =\( \frac{1}{m} \)+\( \frac{1}{n} \)=\( \frac{n+m}{m} \)=\( \frac{m+n}{mn} \) Required time = (\( \frac{mn}{m+n} \)) days
Ans .
(4) \( \frac{4}{3} \)hour
(4) Let A, B and C together do the work in x hours. Time taken by A = (x + 6) hours Time taken by B= (x + 1) hours Time taken by C = 2x hours =>\( \frac{1}{x+6} \)+\( \frac{1}{x+1} \)+\( \frac{1}{2x} \)=\( \frac{1}{x} \) =>\( \frac{1}{x+6} \)+\( \frac{1}{x+1} \)=\( \frac{1}{x} \)-\( \frac{1}{2x} \)=\( \frac{1}{2x} \) =>\( \frac{1}{x+6} \)=\( \frac{1}{2x} \)-\( \frac{1}{x+1} \)=\( \frac{x+1-2x}{2x(x+1)} \) =>\( \frac{1}{x+6} \)=1-x/ 2x2+2x =>2x 2+ 2x = x + 6 – x2 – 6x =>3x 2 + 7x – 6 = 0 => 3x 2 + 9x – 2x – 6 = 0 => 3x (x + 3) – 2 (x + 3) = 0 =>(3x – 2) (x +3) = 0 =>3x – 2 = 0 as x + 3 != 0 => x= \( \frac{2}{3} \) Time taken by A =6+\( \frac{2}{3} \)=\( \frac{18+2}{3} \)=\( \frac{20}{3} \)hours Time taken by B =1+\( \frac{2}{3} \)=\( \frac{5}{3} \)hours (A +B)’s 1 hour’s work=\( \frac{3}{20} \)+\( \frac{5}{3} \)=\( \frac{3+12}{20} \)=\( \frac{15}{20} \)=\( \frac{3}{4} \) Required time =\( \frac{4}{3} \)hour.
Ans .
(2) 96
(2) Time taken by B and C = x days (let) Time taken by A = 3x days Part of work done by A, B and C in 1 day= \( \frac{1}{x} \) +\( \frac{1}{3x} \)=\( \frac{3+1}{3x} \)=\( \frac{4}{3x} \) => \( \frac{4}{3x} \)=\( \frac{1}{24} \) => 3x = 4 × 24 => x= \( \frac{4*24}{3} \)=32days Time taken by A = 32 × 3 = 96 days
Ans .
(4) 3 days
(3) (4) A`s 1 day`s work =\( \frac{1}{4} \) B`s 1 days work = \( \frac{1}{12} \) (A + B)s 1 days work =\( \frac{1}{4} \) +\( \frac{1}{12} \) =\( \frac{3+1}{12} \) =\( \frac{4}{12} \) =\( \frac{1}{3} \) Required time = 3 days.
Ans .
(3) 24 days
(3) A does \( \frac{1}{4} \) work in 10 days A will do 1 work in 10 × 4 = 40 days Similarly, B will do the same work in 20 × 3 = 60 days (A + B)s 1 days work =\( \frac{1}{40} \)+\( \frac{1}{60} \) = \( \frac{3+2}{120} \)=\( \frac{5}{120} \) = \( \frac{1}{24} \) Required time = 24 days .
Ans .
(2)10 hours
(2) Using Rule 1, M1 D1 T1 = M2D2T2 =>15 × 20 × 8 = 20 × 12 × T2 => T2 = \( \frac{15*20*8}{20*12} \) =10 hours.
Ans .
(4) 60 days
4) (Raj + Ram)s 1 days work =\( \frac{1}{10} \) Raj`s 1 days work = \( \frac{1}{12} \) Ram`s 1 day’s work = \( \frac{1}{10} \)-\( \frac{1}{12} \) = \( \frac{6-5}{60} \) = \( \frac{1}{60} \) Required time = 60 days
Ans .
(2) 11 days
(2) A`s 1 days work =\( \frac{1}{9} \) B`s 1 days work = \( \frac{1}{15} \) Work done in first 2 days = A`s 1 days work + B`s 1 days work = \( \frac{1}{9} \)+\( \frac{1}{15} \)= \( \frac{5+3}{45} \) = \( \frac{8}{45} \) Work done in first 10 days = \( \frac{8*5}{45} \) =\( \frac{8}{9} \) Remaining work = 1-\( \frac{8}{9} \) =\( \frac{1}{9} \) Now, it is turn of 'A' for the eleventh day. Time taken by 'A' in doing \( \frac{1}{9} \) work = \( \frac{1}{9} \) *9 = 1 day Required time = 10 + 1 = 11 days.
Ans .
(4) 63
(4) Using Rule 1,
15 men complete \( \frac{1}{3} \)work in 7 days.
Time taken in doing 1 work = 3 × 7 = 21 days
=> M1D
Ans .
(2) 160 minutes
(2) (x and y)s 1 hour work = \( \frac{1}{4} \) +\( \frac{1}{8} \) = \( \frac{2+1}{8} \) = \( \frac{3}{8} \) Required time =\( \frac{8}{3} \) hours = (\( \frac{8}{3} \)*60) minutes. => 160 minutes.
Ans .
(1) 20 hours
(1) Number of pages copied by x in hour =\( \frac{80}{20} \)=4 Number of pages copied by x and y in 1 hour =\( \frac{135}{27} \)= 5 Number of pages copied by y in 1 hour = 5 – 4 = 1 Required time = 20 hours.
Ans .
(2)24
(2) (A + B)s 1 days work = \( \frac{1}{15} \)....(i) (B + C)s 1 days work = \( \frac{1}{12} \) .... (ii) and (C + A)s 1 days work = \( \frac{1}{10} \).... (iii) On adding all three equations, 2 (A + B + C)’s 1 days work = \( \frac{1}{15} \)+\( \frac{1}{12} \)+\( \frac{1}{10} \) =\( \frac{4+6+5}{60} \) =\( \frac{15}{60} \) = \( \frac{1}{4} \) (A + B + C)s 1 days work = \( \frac{1}{8} \)....(iv) By equation (iv) – (ii), A`s 1 days work = \( \frac{1}{8} \)- \( \frac{1}{12} \) = \( \frac{3-2}{24} \) = \( \frac{1}{24} \) Required time = 24 days.
Ans .
(3)\( \frac{19}{30}\)
(3)(A + B)`s 1 days work =\( \frac{1}{25} \)+\( \frac{1}{30} \) = \( \frac{6+5}{150} \)=\( \frac{11}{150} \) (A + B)s 5 days work =\( \frac{5*11}{150} \)=\( \frac{11}{30} \) Remaining work =1-\( \frac{11}{30} \)=\( \frac{30-11}{30} \) =\( \frac{19}{30} \)
Ans .
(3) 9
(3)(A + B)s 1 days work = \( \frac{1}{6} \) A`s 1 days work =\( \frac{1}{18} \) B`s 1 days work =\( \frac{1}{6} \)-\( \frac{1}{18} \)= \( \frac{3-1}{18} \) = \( \frac{2}{18} \) = \( \frac{1}{9} \) Required time = 9 days
Ans .
(2) 12 days
(2) A`s 2 days work = B`s 3 days work Time taken by A = 8 days Time taken by B =\( \frac{8}{2} \) *3 =>12 days.
Ans .
(3) 8 days
Ans .
(2) 8 days
(2)(A + B)s 1 days work =\( \frac{1}{8} \) (B + C)s 1 days work =\( \frac{1}{12} \) and (A + B + C)s 1 days work =\( \frac{1}{6} \) C`s 1 days work = \( \frac{1}{6} \)-\( \frac{1}{8} \)=\( \frac{4-3}{24} \)=\( \frac{1}{24} \) A`s 1 days work =\( \frac{1}{6} \)-\( \frac{1}{12} \)= \( \frac{2-1}{12} \)= \( \frac{1}{12} \) (A + C)s 1 days work =\( \frac{1}{12} \)+\( \frac{1}{24} \)=\( \frac{2+1}{24} \)=\( \frac{1}{8} \) Required time = 8 days
Ans .
(3)\( \frac{7}{9} \)
(3)Using Rule 1, (M1D1T1) / (W1) = (M2D2T2) / (W2) = \( \frac{90*16*12}{1} \) = (70*24*8 ) / (W2) W2 = \( \frac{90*16*12}{70*24*8 }\) = \( \frac{7}{9} \) parts
Ans .
(3)12 days
(3) Let the work be completed in x days. According to the question, \( \frac{x}{16} \)+\( \frac{x-8}{32} \)+\( \frac{x-6}{48} \) =1 \( \frac{6x+3x-24+2x-12 }{96} \) =1 11x – 36 = 96 11x = 96 + 36 = 132 x =\( \frac{132}{11} \) =12 days.
Ans .
(3) 8 days
(3) (A+B)s 1 days work =\( \frac{1}{15} \) (B+C)s 1 days work =\( \frac{1}{10} \) and (A+C)s 1 days work =\( \frac{1}{12} \) On adding all three, 2(A+B+C)s 1 days work =\( \frac{1}{15} \)+\( \frac{1}{10} \)+\( \frac{1}{12} \) =\( \frac{4+6+5}{60} \) =\( \frac{15}{60} \)=\( \frac{1}{4} \) (A + B + C)s 1 days work =\( \frac{1}{8} \) Required time = 8 days.
Ans .
(3 7
(3) Let the whole work be completed in x days A`s 1 days work =\( \frac{1}{10} \) B`s 1 days work =\( \frac{1}{12} \) and C`s 1 days work =\( \frac{1}{15} \) According to the question, A`s (x – 5) days work + B`s (x – 3) days work + Cs x days work = 1 =>\( \frac{x-5}{10} \) +\( \frac{x-3}{12} \) +\( \frac{x}{15} \) = 1 => \( \frac{x-5}{10} \)+\( \frac{x-3}{12} \)+\( \frac{x}{15} \) = 1 => \( \frac{6(x-5)+5(x-3)+4x}{60} \) =1 => 6x – 30 + 5x – 15 + 4x = 60 =>15x – 45 = 60 => 15x = 60 + 45 = 105 => x=\( \frac{105}{15} \) = 7 days.
Ans .
(2)3\( \frac{1}{13} \)days
A`s 1 days work =\( \frac{1}{24} \) B`s 1 days work =\( \frac{1}{5} \) and C 1 days work =\( \frac{1}{12} \) (A + B + C)s 1 days work = \( \frac{1}{24} \) +\( \frac{1}{5} \) +\( \frac{1}{12} \) =\( \frac{5+24+10}{120} \) =\( \frac{39}{120} \) =\( \frac{13}{40} \) Required Time=\( \frac{40}{13} \) =3\( \frac{1}{13} \) days.
Ans .
(4)10 days
Ans .
(1)5\( \frac{1}{7} \)days
(1) A`s 1 days work =\( \frac{1}{9} \) B`s 1 days work = 5\( \frac{1}{12} \) (A + B)s 1 day’s work = \( \frac{1}{9} \)+\( \frac{1}{12} \)= \( \frac{4+3}{36} \) = \( \frac{7}{36} \) Required time = \( \frac{36}{7} \) =5\( \frac{1}{7} \)days.
Ans .
(1) 60 hours
(1) Let time taken by son be x hours. Father’s and son`s 1 days work = \( \frac{1}{30} \)+\( \frac{1}{x} \) \( \frac{1}{30} \)+\( \frac{1}{x} \) =\( \frac{1}{20} \) =>\( \frac{1}{x} \)= \( \frac{1}{20} \)-\( \frac{1}{30} \) =\( \frac{3-2}{60} \)=\( \frac{1}{60} \) => x = 60 hour.
Ans .
(2)9days
(2) Work done by (A + B) in 5 days = 5(\( \frac{1}{12} \)+\( \frac{1}{20} \) ) =5(\( \frac{5+3}{60} \) ) = \( \frac{40}{60} \) =\( \frac{2}{3} \) Remaining work = 1-\( \frac{2}{3} \) =\( \frac{1}{3} \) Time taken by C in doing \( \frac{1}{3} \) work = 3 days Required time = 3 × 3 = 9 days.
Ans .
(3)3\( \frac{15}{16} \)
(3) A`s 1 days work =\( \frac{1}{7} \) B`s 1 days work =\( \frac{1}{9} \) (A + B)s 1 days work =\( \frac{1}{7} \)+\( \frac{1}{9} \) =\( \frac{9+7}{63} \) =\( \frac{16}{63} \) \ Required time =\( \frac{63}{16} \) days =3\( \frac{15}{16} \)days.
Ans .
(1) 12 days
(1) (A + B)s 1 days work =\( \frac{1}{24} \) (A + B + C)s 1 days work =\( \frac{1}{8} \) C`s 1 days work = \( \frac{1}{24} \) -\( \frac{1}{8} \) =\( \frac{3-1}{24} \) =\( \frac{2}{24} \) =\( \frac{1}{12} \) Required time = 12 days.
Ans .
(4) 8 days
(4) (A + B)’s 1 day’s work=\( \frac{1}{12} \)+\( \frac{1}{24} \)=\( \frac{2+1}{24} \)=\( \frac{3}{24} \)=\( \frac{1}{8} \) Required time = 8 days.
Ans .
(4)8
(4) (A + B)s 1 days work =\( \frac{1}{11} \)+\( \frac{1}{20} \) =\( \frac{20+11}{220} \)=\( \frac{31}{220} \) (A + C)’s 1 days work =\( \frac{1}{11} \)+\( \frac{1}{55} \)=\( \frac{5+1}{55} \)=\( \frac{6}{55} \) Work done in first two days = \( \frac{31}{220} \)+\( \frac{6}{55} \) =\( \frac{31+24}{220} \)=\( \frac{55}{220} \)=\( \frac{1}{4} \) Required time = 2 × 4 = 8 days.
Ans .
(1)18 days
(1) (A + B)s 1 days work =\( \frac{1}{6} \) A`s 1 days work =\( \frac{1}{9} \) B’s 1 day’s work =\( \frac{1}{6} \)-\( \frac{1}{9} \)=\( \frac{3-2}{18} \)=\( \frac{1}{18} \) Required time = 18 days.
Ans .
(2) 24 days
A`s 1 days work =\( \frac{1}{18} \) A`s 12 days work =\( \frac{12}{18} \)=\( \frac{2}{3} \) =>Remaining work =1-\( \frac{2}{3} \) =\( \frac{1}{3} \) Time taken by B in doing \( \frac{1}{3} \) work = 8 days Time taken by B in doing whole work = 3 × 8 = 24 days .
Ans .
(3)8 days
(3) (A + B)s 1 days work=\( \frac{1}{8} \) ... (i) (B + C)s 1 days work= \( \frac{1}{12} \).... (ii) and (A + B + C)s 1 days work =\( \frac{1}{6} \)... (iii) By equations (i) + (ii) – (iii), Bs 1 days work =\( \frac{1}{8} \)+\( \frac{1}{12} \)-\( \frac{1}{6} \) = \( \frac{3+2-4}{24} \) = \( \frac{1}{24} \) .... (iv) By equations (iii) – (iv), (A + C)’s 1 days work =\( \frac{1}{6} \)-\( \frac{1}{24} \) = \( \frac{4-1}{24} \)= \( \frac{3}{24} \) =\( \frac{1}{8} \) Required time = 8 days
Ans .
(4)12 days
(4) Let time taken by A be x days. Time taken by B = 3x days According to the question, \( \frac{1}{x} \)+\( \frac{1}{3x} \)=\( \frac{1}{9} \) =>\( \frac{3+1}{3x} \) =\( \frac{1}{9} \) =>3x = 4 × 9 => x = \( \frac{4*9}{3} \) =12 days.
Ans .
(4) 100 days
Ans .
(3)(\( \frac{pq}{p+q} \)
(3) X`s 1 days work =\( \frac{1}{p} \) Y`s 1 day’s work =\( \frac{1}{q} \) (X + Y)s 1 days work= \( \frac{1}{p} \)+\( \frac{1}{q} \)=\( \frac{q+p}{pq} \) Required time =(\( \frac{pq}{p+q} \).
Ans .
(2)\( \frac{40}{9} \)
(2) A`s 1 days work =\( \frac{1}{8} \) B`s 1 days work =\( \frac{1}{10} \) (A + B)s 1 days work = \( \frac{1}{8} \)+\( \frac{1}{10} \) =\( \frac{5+4}{40} \)=\( \frac{9}{40} \) Required time = \( \frac{40}{9} \) days
Ans .
(2) 16 days
(2) (A + B)s 1 days work =\( \frac{1}{36} \) (B + C)s 1 days work = \( \frac{1}{24} \) and (A + C)s 1 days work =\( \frac{1}{18} \) On adding all three, 2 (A + B + C)s 1 days work =\( \frac{1}{36} \)+\( \frac{1}{24} \)+\( \frac{1}{18} \) = \( \frac{2+3+4}{72} \) =\( \frac{9}{72} \) =\( \frac{1} {8} \) (A + B + C)’s 1 day’s work =\( \frac{1}{36} \) Required time = 16 days .
Ans .
\( \frac{xy}{x+y} \) days
(3) Koushik`s 1 days work =\( \frac{1}{x} \) Krishnu`s 1 days work =\( \frac{1}{y} \) One days work of both =\( \frac{1}{x} \)+\( \frac{1}{y} \) =\(\frac{x+y}{xy} \) Required time =\( \frac{xy}{x+y} \) days.
Ans .
(2)8
M1D1 = M2D2 =>24 × 12 = 36 × D2 = D2 =\( \frac{24*12}{36} \) = 8 days.
Ans .
(1)18 days
(3) (A + B)s 1 days work =\( \frac{1}{18} \) (B + C)s 1 days work =\( \frac{1}{24} \) and (C + A)s 1 days work =\( \frac{1}{36} \) On adding all three, 2 (A + B + C)s 1 day’s work =\( \frac{1}{18} \)+\( \frac{1}{24} \)+\( \frac{1}{36} \)=\( \frac{4+3+2}{72} \)=\( \frac{9}{72} \)=\( \frac{1}{8} \) (A + B + C)’s 1 days work =\( \frac{1}{16} \) Required time = 16 days .
Ans .
(1) 10\( \frac{5}{24} \) days
(1) A`s 4 days work = Bs 5 days work => A : B = 4 : 5 Again, B : C = 6 : 7 => A : B : C = 4 × 6 : 5 × 6 : 5 × 7 = 24 : 30 : 35 Q Time taken by A = 7 days Time taken by C =\( \frac{35}{24} \) * 7 =\( \frac{245}{24} \) =10\( \frac{5}{24} \) days.
Ans .
(2)7 days
Ans .
(2)2
(2) Work done by two sons in an hour =\( \frac{1}{3} \)+\( \frac{1}{6} \)=\( \frac{2+1}{6} \)=\( \frac{1}{2} \) Work done by father in an hour =\( \frac{1}{2} \) Required time = 2 hours
Ans .
(4) 4 days
A`s 1 days work =\( \frac{1}{10} \) B`s 1 days work =\( \frac{1}{12} \) and C`s 1 day’s work =\( \frac{1}{15} \) (A + B + C)’s 1 days work = \( \frac{1}{10} \) +\( \frac{1}{12} \) +\( \frac{1}{15} \) =\( \frac{6+5+4}{60} \) =\( \frac{15}{60} \) =\( \frac{1}{4} \) Required time = 4 days.
Ans .
(1) 20 mats
=>5 × 5 × x = 10 × 10 × 5 => x =\( \frac{10*10*5}{5*5} \) = 20 mats.
Ans .
(2)20 days
(2) (A + B)s 1 days work =\( \frac{1}{12} \) As 1 days work =\( \frac{1}{30} \) B`s 1 day’s work =\( \frac{1}{12} \)-\( \frac{1}{30} \) =\( \frac{5-2}{60} \) =\( \frac{1}{20} \) Required time = 20 days
Ans .
(2)48
(2) (Ganesh + Ram + Sohan)s 1 days work =\( \frac{1}{16} \) (Ganesh + Ram)s 1 days work = \( \frac{1}{24} \) Sohan`s 1 days work = \( \frac{1}{16} \) -\( \frac{1}{24} \) =\( \frac{3-2}{48} \) =\( \frac{1}{48} \) Required time = 48 days.
Ans .
(1) 120 days
(1) (A + B)s 1 days work= \( \frac{1}{72} \) ..... (i) (B + C)s 1 days work = \( \frac{1}{120} \).... (ii) and (C + A)’s 1 day’s work = \( \frac{1}{90} \)..... (iii) On adding all three, 2 (A + B + C)s 1 days work =\( \frac{1}{72} \)+\( \frac{1}{120} \)+\( \frac{1}{90} \) =\( \frac{5+3+4}{360} \) =\( \frac{12}{360} \)=\( \frac{1}{30} \) (A + B + C)s 1 days work= \( \frac{1}{60} \)..... (iv) A`s 1 days work = Equation (iv) – (ii), \( \frac{1}{60} \)-\( \frac{1}{120} \)=\( \frac{2-1}{120} \)=\( \frac{1}{120} \) Required time = 120 days .
Ans .
(2)28
Ans .
(3)17\( \frac{1}{7} \) days
(3) A`s 1 days work =\( \frac{1}{30} \) B`s 1 days work =\( \frac{1}{40} \) (A + B)’s 1 day’s work =\( \frac{1}{30} \)+\( \frac{1}{40} \)= \( \frac{4+3}{120} \)=\( \frac{7}{120} \) Required time =\( \frac{120}{7} \)=17\( \frac{1}{7} \).
Ans .
(2) 5\( \frac{1}{3} \)days
(2) A can finish the work in 18 days. A`s one days work = \( \frac{1}{18} \) Similarly, B`s one days work = \( \frac{1}{24} \) (A + B)s 8 days work =( \( \frac{1}{18} \)+\( \frac{1}{24} \)) *8 =\( \frac{7}{72} \) *8=\( \frac{7}{9} \) Remaining work = 1-\( \frac{7}{9} \)=\( \frac{2}{9} \) Time taken to finish the remaining work by B is \( \frac{2}{9} \) *24 = \( \frac{16}{3} \) =5\( \frac{1}{3} \)days.
Ans .
(4) 13 days
(4) (A+B)s 2 days work =2(\( \frac{1}{12} \) +\( \frac{1}{18} \) ) =\( \frac{10}{36} \) Remaining work = 1 - \( \frac{10}{36} \) =\( \frac{26} {36} \) Time taken by B to complete \( \frac{26}{36} \) part of work =>\( \frac{26}{36} \) *18= 13 days.
Ans .
(3) 6 days
(3) A1s one days work = \( \frac{1}{6} \) B`s one days work =\( \frac{1}{12} \) (A + B)s one days work =\( \frac{1}{6} \) +\( \frac{1}{12} \) =\( \frac{2+1}{12} \) =\( \frac{1}{4} \) (A + B)s three days work =\( \frac{3}{4} \) Remaining work = 1-\( \frac{3}{4} \)= \( \frac{1}{4} \) Total required number of days = \( \frac{1}{4} \)*\( \frac{12}{1} \) +3= 3 + 3 = 6 days.
Ans .
(1) 18 days
(1) (A + B)s days work =\( \frac{1}{30} \) (B + C)s 1 days work =\( \frac{1}{24} \) and (C + A)s 1 days work =\( \frac{1}{20} \) 2 (A + B + C)s 1 days work =\( \frac{1}{30} \)+\( \frac{1}{24} \)+\( \frac{1}{20} \) =\( \frac{4+5+6}{120} \)=\( \frac{15}{120} \)=\( \frac{1}{8} \) (A + B + C)s 1 days work =\( \frac{1}{16} \) (A + B + C)s 10 days’ work =\( \frac{10}{16} \)=\( \frac{5}{8} \) Remaining work = 1 -\( \frac{5}{8} \) =\( \frac{3}{8} \) This part of work is done by A alone. Now A`s 1 day’s work =\( \frac{1}{16} \) -\( \frac{1}{24} \) =\( \frac{3-2}{48} \) =\( \frac{1}{48} \) The required no. of days =\( \frac{3}{8} \)* 3= 18 days.
Ans .
(2)60 days
2) (A+B)s 1 days work =\( \frac{1}{30} \) (A + B)s 20 days work =\( \frac{20}{30} \) =\( \frac{2}{3} \) Remaining work =1-\( \frac{2}{3} \)=\( \frac{1}{3} \) Now,\( \frac{1}{3} \)part of work is done by A in 20 days. Whole work will be done by A alone in 20 × 3 = 60 days
Ans .
(3) 4
Ans .
(3) 10 days
(3) Work done by (B + C) in 3 days = 3* (\( \frac{1}{9} \) +\( \frac{1}{12} \)) = \( \frac{1}{3} \)+\( \frac{1}{4} \)=\( \frac{4+3}{12} \)=\( \frac{7}{12} \) Remaining work = 1-\( \frac{7}{12} \) =\( \frac{5}{12} \) This part of work is done by A alone. Now, \( \frac{1}{24} \) part of work is done by A in 1 day. => \( \frac{5}{12} \) part of work will be done by A in = 24 ´*\( \frac{5}{12} \) = 10 days.
Ans .
(2) 24 days
(2) Originally, let there be x men Now, more men, less days (x + 6) : x : : 55 : 44 so,\( \frac{x+6}{x} \)=\( \frac{55}{44} \) =\( \frac{5}{4} \) or 5x = 4x + 24 or x = 24.
Ans .
(3) 12 days
(3) Work done by 2 (A + B) in one day =( \frac{1}{10} \)+( \frac{1}{15} \) =( \frac{3+2}{30} \)=( \frac{5}{30} \)=( \frac{1}{6} \) Work done by (A + B) in oneday =( \frac{1}{12} \) (A + B) can complete the work in 12 days
Ans .
(3)8 days
(3) Let A worked for x days. According to question \( \frac{x}{28} \)+\( \frac{(x+17)}{35} \) =1 =>\( \frac{5x+4(x+17)}{140} \) =1 =>5x + 4x + 68 = 140 =>9x = 140 – 68 = 72 => x = 8 A worked for 8 days
Ans .
(3)12 days
(3) Work done by (A + B) in 1 day =\( \frac{1}{15} \)+\( \frac{1}{10} \)=\( \frac{2+3}{30} \)=\( \frac{1}{6} \) (A + B)s 2 days work =\( \frac{2}{6} \) =\( \frac{1}{3} \) Remaining work =1 -\( \frac{1}{3} \) =\( \frac{2}{3} \) This part is done by A alone. one work is done by A in 15 days. \( \frac{2}{3} \) work is done in 15*\( \frac{2}{3} \) = 10 days. Total number of days = 10 + 2 = 12 days
Ans .
(4)10 days
(1) A`s 1 day`s work =\( \frac{1}{20} \). A`s 4 days work =\( \frac{4}{20} \) =\( \frac{1}{5} \) This part is completed by A and B together. Now, (A + B)s 1 days work = \( \frac{1}{20} \)+\( \frac{1}{12} \)=\( \frac{3+5}{60} \)=\( \frac{8}{60} \)=\( \frac{2}{15} \) Now,\( \frac{2}{15} \)work is done by (A +B) in 1 day. \( \frac{4}{5} \) work is done in . =\( \frac{15}{2} \)*\( \frac{4}{5} \) = 6 days Hence, the work lasted for 4 + 6 = 10 days.
Ans .
(2)9 days
(2) (A + B)s 1 days work =(\( \frac{1}{45} \) +\( \frac{1}{40} \) ) =\( \frac{8+9}{360} \) =\( \frac{17}{360} \) Work done by B in 23 days = \( \frac{1}{4} \) * 23 =\( \frac{23}{40} \) Remaining work = 1- \( \frac{23}{40} \)= \( \frac{17}{40} \) Now,\( \frac{17}{40} \)work was done by (A + B) in 1 day \( \frac{17}{40} \) work was done by (A + B) in 1 * \( \frac{360}{17} \) *\( \frac{17}{40} \) = 9 days. Hence, A left after 9 days.
Ans .
(1)72 days
Ans .
(3)16 days
(3) Time taken by A = \( \frac{8*12}{4} \) = 24days. Work done of by B = \( \frac{4}{12} \)=\( \frac{1}{3} \) Remaining work =1-\( \frac{1}{3} \) = \( \frac{2}{3} \) A can complete a work in 24 days A can complete \( \frac{2}{3} \) part of work in 24* \( \frac{2}{3} \) = 16 days.
Ans .
(1)14\( \frac{1}{3} \) days
(1) A`s 1 days work = \( \frac{1}{12} \) B`s 1 days work = \( \frac{1}{18} \) Part of work done by A and B in first two days = \( \frac{1}{12} \)+ \( \frac{1}{18} \)= \( \frac{3+2}{36} \)= \( \frac{5}{36} \) Part of work done by A and B in 14 days =\( \frac{35}{36} \) [14 days to be taken randomly] Remaining work = 1-\( \frac{35}{36} \) =\( \frac{1}{36} \) Now A will work for 15th day. A will do the \( \frac{1}{36} \) work in \( \frac{1}{36} \)*12 =\( \frac{1}{3} \) day. Total Work will be done in 14\( \frac{1}{3} \) days.
Ans .
(3)7 days
(3) Let the work be completed in x days. According to the question ,\( \frac{x-5}{10} \)+\( \frac{x-3}{12} \)+\( \frac{x}{15} \)=1 =>\( \frac{6x-30+5x-15+4x}{60} \) =1 =>15x – 45 = 60 ,/br> => 15x = 105 => x =\( \frac{105}{15} \) = 7 days.
Ans .
(4)8 days
Ans .
(1)56\( \frac{2}{3} \) days
Ans .
(4)9 days
(4) Let the work be finished in x days. According to the question, A worked for x days while B worked for (x – 3) days \( \frac{x}{18} \)+\( \frac{x-3}{12} \)=1 =>\( \frac{2x+3x-9}{36} \) = 1 => 5x – 9 = 36 => 5x = 45 => x = \( \frac{45}{5} \)= 9 Hence, the work was completed in 9 days.
Ans .
(1)6 days
(1) Let A and B worked together for x days According to the question, Part of work done by A for (x + 10) days + part of work done by B for x days = 1 => \( \frac{x+10}{20} \) +\( \frac{x}{30} \) = 1 => \( \frac{3x+30+2x}{60} \) = 1 =>5x + 30 = 60 => 5x = 30 => x= \( \frac{30}{5} \) = 6 days.
Ans .
(2)8 days
(2) Let the work be completed in x days. According to the question, A worked for (x –3) days, while B worked for x days. \( \frac{x-3}{9} \) +\( \frac{x}{18} \) = 1 =>\( \frac{2x-6+x}{18} \) = 1 => 3x–6 = 18 =>3x = 18 + 6 = 24 => x =\( \frac{24}{3} \) = 8 days.
Ans .
(3)15 days
(3) (B + C)s 2 days work= 2(\( \frac{1}{30} \) + (\( \frac{1}{20} \)) = 2(\( \frac{2+3}{60} \)) = \( \frac{1}{6} \) part Remaining work = 1- \( \frac{1}{6} \)= \( \frac{5}{6} \) part. Time taken by A to complete this part of work \( \frac{5}{6} \) *18 = 15 days.
Ans .
(3)6 days
(3) Part of work done by B in 10 days = 10*\( \frac{1}{15} \) = \( \frac{2}{3} \) Remaining work =1 - \( \frac{1}{2} \) = \( \frac{1}{3} \) Time taken by A = \( \frac{1}{3} \)*18 = 6 days.
Ans .
(3)10\( \frac{1}{4} \)days
(3) Part of work done by A and B in first two days \( \frac{1}{9} \) +\( \frac{1}{12} \) = \( \frac{4+3}{36} \) = \( \frac{7}{36} \) Part of work done in first 10 days = \( \frac{35}{36} \) Remaining work= 1-\( \frac{35}{36} \) = \( \frac{1}{36} \) Now it is the turn of A. Time taken by A =\( \frac{1}{36} \)*9 = \( \frac{1}{4} \)day Total time = 10 +\( \frac{1}{4} \) =10\( \frac{1}{4} \)days.
Ans .
(4)15 days
(4) B`s 1 days work =\( \frac{1}{12} \)-\( \frac{1}{20} \)= \( \frac{5-3}{60} \) =\( \frac{1}{30} \) B`s \( \frac{1}{2} \)days work = \( \frac{1}{60} \) (A + B)s 1 days work = \( \frac{1}{20} \) + \( \frac{1}{60} \) = \( \frac{3+1}{60} \)= \( \frac{1}{15} \) [ B works for half day daily] Hence, the work will be completed in 15 days
Ans .
(3)6 days
. (3) Part of the work done by A and B in 4 days = 2*(\( \frac{1}{12} \)+\( \frac{1}{15} \)) = 4\( \frac{5+4}{60} \) = 4*\( \frac{9}{60} \) =\( \frac{3}{5} \) Remaining work = 1-\( \frac{3}{5} \) =\( \frac{2}{5} \) Time taken by B to complete the remaining work =\( \frac{2}{5} \) *15 =6 days
Ans .
(1)13\( \frac{1}{3} \) days
(1) Part of the work done by X in 8 days=\( \frac{8}{40} \)=\( \frac{1}{5} \) Remaining work = 1-\( \frac{1}{5} \)=\( \frac{4}{5} \) This part of work is done by Y in 16 days. Time taken by Y in doing 1 work =\( \frac{16*5}{4} \) = 20 days. Work done by X and Y in 1 day = \( \frac{1}{40} \)+\( \frac{1}{20} \)=\( \frac{1+2}{40} \)=\( \frac{3}{40} \) Hence, both together will complete the work in\( \frac{40}{3} \) i.e13\( \frac{1}{3} \) days
Ans .
(1)9\( \frac{3}{8} \) days
(1) Work done in first two days =\( \frac{2}{30} \)+\( \frac{1}{10} \)+\( \frac{1}{20} \)=\( \frac{1}{15} \)+\( \frac{1}{20} \)+\( \frac{1}{10} \) =\( \frac{4+3+6}{60} \) = \( \frac{13}{60} \) Work done in first 8 days =\( \frac{52}{60} \) Remaining work = 1-\( \frac{52}{60} \) = \( \frac{8}{60} \) = \( \frac{2}{15} \) (A + B)s 1 days work = \( \frac{1}{30} \) +\( \frac{1}{20} \)=\( \frac{2+3}{60} \)=\( \frac{1}{12} \) Remaining work =\( \frac{2}{15} \) -\( \frac{1}{12} \) =\( \frac{8-5}{60} \)=\( \frac{3}{60} \)=\( \frac{1}{20} \) (A + C)s 1 days work =\( \frac{1}{30} \)+\( \frac{1}{10} \)=\( \frac{1+3}{30} \)=\( \frac{2}{15} \) Time taken =\( \frac{1}{20} \)*\( \frac{15}{2} \) =\( \frac{3}{8} \) day. Total time = 9 +\( \frac{3}{8} \) =9\( \frac{3}{8} \) days
Ans .
(1)5 days
(1) Work done by B in 9 days = \( \frac{9}{12} \) =\( \frac{3}{4} \)part Remaining work = 1- \( \frac{3}{4} \)= \( \frac{1}{4} \)which is done by A Time taken by A =\( \frac{1}{4} \)*20 = 5days.
Ans .
(2) 7\( \frac{1}{3} \) days
(2) Work done by A in 6 days =\( \frac{6}{8} \)=\( \frac{3}{4} \)part Work destroyed by B in 2 days =\( \frac{2}{3} \)part Remaining work after destruction = \( \frac{3}{4} \)- \( \frac{2}{3} \)= \( \frac{9-8}{12} \)=\( \frac{1}{12} \) Now, time taken by A in doing \( \frac{11}{12} \) part \( \frac{11}{12} \) * 8 = \( \frac{22}{3} \) =7\( \frac{1}{3} \)days.
Ans .
(1)6 days
(1) Work done by B in 10 days =\( \frac{10}{15} \)=\( \frac{2}{3} \) Remaining work = 1-\( \frac{2}{3} \)=\( \frac{1}{3} \) Time taken by A to complete the work = \( \frac{1}{3} \) *18 = 6 days.
Ans .
(1)48 days
Ans .
(3) 120 days
(3) (A + B + C)s 1 days work = \( \frac{1}{20} \)+\( \frac{1}{30} \)+\( \frac{1}{60} \) = \( \frac{3+2+1}{60} \) = \( \frac{1}{10} \) A`s 2 days work =\( \frac{2}{20} \)=\( \frac{1}{10} \) Work done in first three days= \( \frac{1}{10} \)+\( \frac{1}{10} \)=\( \frac{2}{10} \)=\( \frac{1}{5} \) [A`s work for 2 days + (A + B + C) work on 3rd day] Hence, the work will be finished in 15 days.
Ans .
(3)6 days
(3) (A + B)`s 2 days work =\( \frac{2}{3} \) Remaining Work =1 - \( \frac{2}{3} \) = \( \frac{1}{3} \) Time taken by A in destroying \( \frac{1}{3} \)work = 2 days Time taken by A in completing the work = 6 days B`s 1 days work = \( \frac{1}{3} \)-\( \frac{1}{6} \) =\( \frac{2-1}{6} \) =\( \frac{1}{6} \) B alone will complete the work in 6 days.
Ans .
(3)24 days
(3) Work done by A and B in 7 days=\( \frac{7}{20} \)+\( \frac{7}{30} \)=\( \frac{21+14}{60} \)=\( \frac{35} {60} \)=\( \frac{7}{12} \) So, Remaining work = 1-\( \frac{7}{12} \) =\( \frac{5}{12} \) Time taken by C= \( \frac{12}{5} \)*10 = 24 days.
Ans .
(3)6\( \frac{2}{3} \)days
Ans .
(4) 4
(4) Work done by A and B in first 6 days = (A + B)s 4 days work + B`s 2 days work =4*\( \frac{1}{8} \)+\( \frac{1}{12} \) =\( \frac{1}{2} \)+\( \frac{1}{6} \)= \( \frac{3+1}{6} \) =\( \frac{2}{3} \) Remaining work = 1-\( \frac{2}{3} \) =\( \frac{1}{3} \) Time taken by C =\( \frac{1}{3} \)*12 = 4days.
Ans .
(1)60 days
(1) (A + B) together do the work in 30 days (A + B)s 1 days work =\( \frac{1}{30} \) (A + B)s 20 days work =\( \frac{20}{30} \) =\( \frac{2}{3} \) Remaining work =1-\( \frac{2}{3} \) = \( \frac{1}{3} \) Time taken by A in doing \( \frac{1}{3} \) work = 20 days Time taken in doing 1 work= 20 × 3 = 60 days.
Ans .
(3) 3\( \frac{1}{2} \)days
(3) Remaining work =1-\( \frac{1}{8} \) =\( \frac{7}{8} \) (A + B)s 1 days work =\( \frac{1}{6} \)+\( \frac{1}{12} \)=\( \frac{2+1}{12} \)=\( \frac{3}{12} \)=\( \frac{1}{4} \) Time taken in doing \( \frac{7}{8} \)part of work =\( \frac{7}{8} \)*4= \( \frac{7}{2} \)= 3\( \frac{1}{2} \)days
Ans .
(2)6
(2) Work done by 12 men in 8 days = Work done by 16 women in 12 days. => 12 × 8 men => 16 × 12 women =>1 man => 2 women Now, work done by 12 men in 1 day =\( \frac{1}{8} \) 1 mans 1 days work = \( \frac{1}{12*8} \) =\( \frac{1}{96} \) 16 mens 3 days work
Ans .
(2)8
Ans .
(1) 44
12 men =24 boys =>1 man = 2 boys => 15 men + 6 boys = 30 boys + 6 boys = 36 boys =>M1D1 =M2D2 =>24 × 66 = 36 × D2 D2 =\( \frac{24*66}{36} \) = 44 days.
Ans .
(3) 100 days
(3) A, B and C together complete the work in 40 days. (A + B + C)s 1 days work = \( \frac{1}{40} \) (A + B + C)s 16 days work=\(\frac{16}{40} \)=\(\frac{2}{5} \) Remaining Work = 1-\(\frac{2}{5} \)=\(\frac{3}{5} \) This part of work is done by B and C in 40 days. =>Time taken in doing \(\frac{3}{5} \) work = 40 days. =>Time taken in doing in 1 work = \(\frac{40 *5}{3} \)=\(\frac{200}{3} \)days. A`s days work = (A + B + C)s 1 days work - (B + C)s 1 days work = \(\frac{1}{40} \)+ \(\frac{3}{200} \)=\(\frac{5-3}{200} \)= \(\frac{2}{200} \)= \(\frac{1}{100} \) Required time = 100 days.
Ans .
(2)40
(2) Number of men originally = x (let) =>M1D1=M2D2 => × 60 = (x + 8) × 50 =>6x = 5x + 40 =>6x – 5x = 40 =>x = 40 men
Ans .
(4) 60
(4) Using Rule 1,, Number of men originally = x (let) =>M1D1=M2D2 => x × 18 = (x – 6) × 20 =>x × 9 = (x – 6) × 10 = 10x – 60 =>10x – 9x = 60 => x = 60 men
Ans .
(4)75
(4) Original number of men= x (let) =>M1D1=M2D2 =>x × 40 = (x + 45) × 25 =>8x = (x + 45) × 5 =>8x = 5x + 225 => 8x – 5x = 225 => 3x = 225 => x= \( \frac{225}{3} \)= 7 men.
Ans .
(2) 9 days
(2) Let A left the work after x days. According to the question, Work done by A in x days + work done by B in (23 + x ) days = 1 => \( \frac{x}{45} \) +\( \frac{23+x}{40} \)=1 =>\( \frac{8x+207+9x}{360} \) = 1 =>17x + 207 = 360 => 17x = 360 – 207 = 153 => x = \( \frac{153}{17} \) = 9days.
Ans .
(2) 12
Ans .
(4) 11
(4) Let the work be completed in x days. According to the question, C worked for (x – 4) days. = \( \frac{x}{24} \) +\( \frac{x}{30} \)=\( \frac{x-4}{40} \)=1 =>\( \frac{5x+4x+3(x-4)}{120} \) =1 =>\( \frac{12x-12}{120} \) = 1 =>\( \frac{12(x-1)}{120} \)= 1 =>\( \frac{x-1}{10} \) =>x – 1 = 10 => x = 10 + 1 = 11 days.
Ans .
(2)24
(2) (A + B)s 1 days work = \( \frac{1}{15} \)....(i) (B + C)s 1 days work = \( \frac{1}{12} \) .... (ii) and (C + A)s 1 days work = \( \frac{1}{10} \).... (iii) On adding all three equations, 2 (A + B + C)’s 1 days work = \( \frac{1}{15} \)+\( \frac{1}{12} \)+\( \frac{1}{10} \) =\( \frac{4+6+5}{60} \) =\( \frac{15}{60} \) = \( \frac{1}{4} \) (A + B + C)s 1 days work = \( \frac{1}{8} \)....(iv) By equation (iv) – (ii), A`s 1 days work = \( \frac{1}{8} \)- \( \frac{1}{12} \) = \( \frac{3-2}{24} \) = \( \frac{1}{24} \) Required time = 24 days.
Ans .
(2)24
(2) Number of men initially = x (let) =>M1D1=M2D2 => x × 40 = (x + 8) × 30 =>4x = 3x + 24 =>4x – 3x = 24 =>x = 24 men
Ans .
(3) 36 days
(3) Let Y alone complete the work in x days. According to the question, X`s 16 days work + Y`s 12 days work = 1 => \( \frac{16}{24} \) +\( \frac{12}{x} \) =1 =>\( \frac{2}{3} \) +\( \frac{12}{x} \) =1 =>\( \frac{12}{x} \) = 1 -\( \frac{2}{3} \) =\( \frac{1}{3} \) =>x = 12 × 3 = 36 days
Ans .
(3)40 days
Ans .
(2)1\( \frac{2}{3} \)days
(2) Work done by A and B in 5 =5(\( \frac{1}{10} \)+\( \frac{1}{15} \)) =5(\( \frac{3+2}{30} \)) = 5*\( \frac{5}{30} \) =\( \frac{5}{6} \) Remaining Work = 1- \( \frac{5}{6} \) =\( \frac{1}{6} \) Time taken by A =\( \frac{1}{6} \)*10 = \( \frac{5}{3} \) days.=1\( \frac{2}{3} \) days.
Ans .
(4)60 days
(4) (A + B)’s 1 day’s work = \( \frac{1}{30} \) (A + B)s 20 days’ work =\( \frac{20}{30} \) =\( \frac{2}{3} \) Remaining Work =1- \( \frac{2}{3} \) =\( \frac{1}{3} \) Time taken by A in doing \( \frac{1}{3} \) of work = 20 days Time taken by A in doing whole work = 3 × 20 = 60 days
Ans .
(4)4 days
(4) Nuts cut by Ram and Hari in 1 day =\( \frac{12}{2} \)kg. = 6 kg. ....(i) Nuts cut by them in 5 days = 30 kg. Amount of nuts cut by Ram alone = 58 – 30 = 28 kg. Time = 8 days Nuts cut by Ram in 1 day =\( \frac{28}{8} \) = 3.5 kg. From equation (i), Nuts cut by Hari in 1 day = (6 – 3.5) kg. = 2.5 kg. Time taken by Hari in cutting 10 kg. of nuts = \( \frac{10}{2.5} \)= 4 days
Ans .
(4)30 days
(4) Ramesh`s 1 days work =\( \frac{1}{20} \) Rahman`s 1 days work = \( \frac{1}{25} \) (Ramesh + Rahman)s 1 days work = \( \frac{1}{20} \)+\( \frac{1}{25} \)= \( \frac{5+4}{100} \)=\( \frac{9}{100} \) Their 10 days work =\( \frac{90}{100} \)=\( \frac{9}{10} \) Remaininf Work = 1- \( \frac{9}{10} \) =\( \frac{1}{10} \) Suresh does\( \frac{1}{10} \) work in 3 days. Time taken by Suresh in doing 1 work = 3 × 10 = 30 days
Ans .
(3) 40 days
(3) Let C alone complete the work in x days. According to the question, A`s 7 days work + B`s 3 days work + C`s 2 days work = 1 => \( \frac{7}{10} \)+\( \frac{3}{12} \)+\( \frac{2}{x} \) =1 =>\( \frac{2}{x} \)= 1 -\( \frac{7}{10} \)-\( \frac{1}{4} \) =>\( \frac{20-14-5}{20} \) =\( \frac{1}{20} \) => x = 2 × 20 = 40 days.
Ans .
(2) 12
(2) Let the number of working men be x. => M1D1=M2D2 => x × 60 = (x + 6) × 40 => 3x = 2x + 12 => 3x – 2x = 12 => x = 12
Ans .
(4) 12 days
. (4) A`s 1 days work =\( \frac{1}{20} \) B`s 1 days work =\( \frac{1}{15} \) (A + B + C)s 1 days work =\( \frac{1}{5} \) C`s 1 day`s work =\( \frac{1}{5} \)-\( \frac{1}{20} \)-\( \frac{1}{15} \) =\( \frac{12-3-4}{60} \)=\( \frac{5}{60} \)=\( \frac{1}{12} \) Required time = 12 days.
Ans .
(3)30
. (3) Let 5 men leave the work after x days. =>M1D1=M2D2+M3D3 =>15 × 40 = 15 × x + 10 × (45 – x) => 600 = 15x + 450 – 10x => 600 – 450 = 5x => 5x = 150 => x =\( \frac{150}{5} \)= 30 days.
Ans .
(1)24days
(1)(A + B)s 1 days work =\( \frac{1}{12} \) (A + B)’s 5 days’ work = \( \frac{5}{12} \) Remaining work = 1- \( \frac{5}{12} \) = \( \frac{7}{12} \) A does\( \frac{7}{12} \) work in 14 days. A will do 1 work in =\( \frac{14*12}{7} \)= 24 days.
Ans .
(2) 4 days
(3) According to question, (6M + 8B)10 = (26M + 48B)2 60M + 80B = 52M + 96B or, 1M = 2B ; 5M + 20B = (30 + 20)B = 50 boys and 6M + 8B => (12 + 8) boys = 20 boys 20 boys can finish the work in 10 days, 50 boys can finish the work in \( \frac{20*10}{50} \) days = 4 days
Ans .
(2) 5 days
(2) 5*6 men = 10*5 women => 3 men = 5 women; 5 women + 3 men = 6 men; 5 men complete the work in 6 days 6 men will complete the work in \( \frac{5*6}{6} \) = 5 days.
Ans .
(3) 3 days
. (3) 3m = 6w => 1m = 2w; 12m + 8w = (12*2w) + 8w = 32w; 6 women can do the work in 16 days 32 women can do the work in \( \frac{16*6}{32} \) = 3 days
Ans .
(4) 41 days
. (4) 1 mans 1 days work = \( \frac{1}{3} \) 1 womans 1 days work = \( \frac{1}{4} \) 1 boys 1 days work = \( \frac{1}{4} \) (1 man + 1 woman)s days work = \( \frac{1}{4} \)*[\( \frac{1}{3} \) + \( \frac{1}{4} \)] =\( \frac{7}{48} \) Remaining work = 1-\( \frac{7}{48} \)=\( \frac{41}{48} \). Now; 1 boys \( \frac{1}{4} \) days work = \( \frac{1}{4} \)*\( \frac{1}{12} \)= \( \frac{1}{48} \) \( \frac{41}{48} \) work will be done by \( \frac{41}{48} \)*48 = 41 boys
Ans .
(4) 10 days
4) 16 men = 20 women => 4 men = 5 women. Now, according to question, 16 men complete the work in 25 days. 1 man one days work = \( \frac{1}{25*16} \) => 4 men one days work = \( \frac{4}{25*16} \) = \( \frac{1}{100} \). Similarly, 1 woman one days work = \( \frac{1}{25*20} \) => 5 women one days work = \( \frac{5}{25*20} \) = \( \frac{1}{100} \) => 28 men = \( \frac{28}{4} \)*5 = 35 women => [28 men + 15 women] => 50 women one days work = \( \frac{50}{25*20} \) = \( \frac{1}{10} \) Therefore, 28 men and 15 women can complete the whole work in 10 days.
Ans .
(3) 13\( \frac{1}{3} \) days
(3) According to the question, 5 men = 8 women 2 men = \( \frac{8}{5} \)*2 = \( \frac{16}{5} \) Total women = \( \frac{16}{5} \)+4 = \( \frac{36}{5} \) No. of days to do the same work = \( \frac{8*12*5}{36} \) = \( \frac{40}{3} \) = 13\( \frac{1}{3} \)
Ans .
(4) 12 days
(4) 3 men = 4 women 1 man = \( \frac{4}{3} \) women 7 men = \( \frac{7*4}{3} \) = \( \frac{28}{3} \) 7 men + 5 women = \( \frac{28}{3} \)+5 = \( \frac{28+15}{3} \) = \( \frac{43}{3} \) Women Now, M1D1 = M2D2 => 4 * 43 = \( \frac{43}{3} \)*D2, where D2 = number of days => D2 = \( \frac{4*3*43}{43} \) = 12 days.